Overview
According to Article 40 (2) of the Enforcement Rules of the Tourism Promotion Act, the inspection to recheck safety status of amusement facilities or machines with the following cases;
- Amusement facilities or machines that have been failed by safety inspection
- Amusement facilities or machines in which an accident occured
- Amusement facilities or machines that have been suspended for more than three months
- Amusement facilities or machines for which the sum of the period of suspension for the last six months is three months or more
Inspection process
- 1. Amusement facility of machine with the following cases cannot operate until it passes Re-Inspection;
- Amusement facilities or machines that have been failed by a Periodical Inspection
- Amusement facilities or machines in which an accident occured
- Amusement facilities or machines that have been suspended for more than three months
- 2. A applicant shall submit a Re-Inspection application form(with the amusement installations survey report) with the following documents to KTC by no later than 20 days before the desired date of Re-Inspection;
- Accident report (if there has been an accident)
- The last safety inspection report
Re-inspection process
Visit the website of the responsible department
Click the button below to jump to the main webpage of the responsible department, where you can find the contact information of the officers in charge.